PEAK
SPD15 - PRODUCTION PLATFORM RIGLESS PROJECT
Client: Dana Energy, PDK
Date: March 2015
Description:
- • Manufacturing a Custom designed King Posts.
- • Reinforcing the Platform Bridges as per technical drawing.
- • Installing the King Posts on the reinforced structure.
- • Rig up the 85ft. High rate burner booms, in collaboration with PDK Co.
- • Providing cooling services during well test operations
SPD16 - PRODUCTION PLATFORM RIGLESS PROJECT
Client: Dana Energy, PDK
Date: March 2015
Description:
- • Manufacturing a Custom designed King Posts.
- • Reinforcing the Platform Bridges as per technical drawing.
- • Installing the King Posts on the reinforced structure.
- • Rig up the 85ft. High rate burner booms, in collaboration with PDK Co.
- • Providing cooling services during well test operations